February 9th, 2011
Sunday Work Party at Ongar
January 24th, 2011
Progress Update – Mid Jan 2011
The weekday teams have continued their work at Ongar. The stations team have been continuing with the benches for the station, and also the sealing the flooring in the museum display area. They are now turning their attentions to the Booking Hall, painting the section above the picture rail now that the re-plastering has been completed.
The Carriage team have also been busy, and are making excellent progress with the 117, with many doors now having their drop-light windows serviced, fixed and new plywood panels cut, shaped and fitted. A painstaking job, but once completed really freshens up the interior of the unit, for what we hope will be another 50 years of service.
The Loco team are on the final stages of the interior restoration of the Ruston shunter, with the many hours of hard work on the preparing, now paying off with an excellent finish being obtained on the cab interior. In addition teams were working on D6729, adjusting the handbrake and attending to a few other incidental items.
The weekend saw work parties at North Weald and Ongar. At Ongar the team continued work on the 117 and also on some of the furniture for the station. The Pway team were working just east of North Weald, where there are a few track alignment issues, and they managed to take out a number of “twists” in the rail to smooth the ride.
At North Weald on Saturday the signals gang worked on the last of the electric interlocking modifications, while other members of the team wire-brushed, rust treated and painted signals parts, many of which were stored beside the heater over-night to allow them to be installed on Sunday. This enabled two of the platform starters to start to be installed as shown below…
January 17th, 2011
Progress Update – Early Jan 2011
It has been another busy few weeks at EOR, and I am glad to be reporting progress on many important areas towards us once again running steam and diesel passenger services.
The station restoration team have been continuing work on the Grade II listed station at Ongar. This has seen the culmination of 12 months work with last of the rooms being transformed into GER colours. This particular room is being fitted to be the “Meeting & Training Room”, and so will provide space for both meetings, an area to host guests, displays and presentations as well as somewhere we can use for mutual improvement classes to train our staff.
The floor in the Museum & Display area is also seeing its final coats, the display cases being investigated and benches for the general waiting room and ladies waiting room have been carefully dismantled, sanded, primed and top-coated over the last few weeks. Both benches now look excellent, and very fitting in Great Eastern brown.
Our appeal to make GER benches for our platforms (with replica cast iron ends) has been successful, with enough monies donated for three benches. Our thanks to all those who donated, and we are shortly going to the foundry to get the ends. The priming and fitting the wood, will be a nice “inside” task for the wetter work days!
Our carriage team are also continuing progress on the 117 DMU, which is now being fitted out with new plywood panels. These are being varnished, to replicate how the Ongar end of the unit used to look when first built for BR. This work requires a keen eye, a steady hand on the saw, and also a little mathematical thought to get the most out of the materials! Work is also continuing on the two Mk2a TSO’s at Ongar, and I am pleased to report that work has also started on two of the vacuum braked coaches currently stored at North Weald as we get these ready for passengers.
The loco and engineering departments have also been busy, with the Ruston cab starting to come together. After many painstaking hours of preparing the insides, carefully working around the loco control handles, removing the many old layers of paint, the hard work really pays off with the first coat of primer transforming the cab into a fresh and welcoming interior. Over the coming weeks, we are looking forward to seeing this loco’s restoration completed.
Maintenance tasks continue, even though the railway is not running passenger trains, and there are jobs being completed on 03170, D6729 (37029) and the Thumper (205205). In addition brake tests have been completed on the two Mk2 FO’s, as our team work through basic inspections and maintenance of all our coaches to ready them for passenger service.
The Pway team have been continuing through the wintry weather, and have been working on levelling the track alignment on the approaches to Blake Hall. Meanwhile track laying at Ongar has continued, and as reported on the news page, the double slip has now been assembled and positioned. This space-saving item enables us to get trains into Platform 1 & 2 (formally goods platforms), as well as have a headshunt to enable “shunt & release” operations for loco hauled stock arriving into these platforms. Work is continuing this week to get the tracks, run-round and loco shed re-connected to the main line.
As part of the crane operations, the former Spelbrook signalbox has been lifted onto its intended foundation, and while it still needs to have its legs fabricated and attached, it starts to give a flavour of how the original used to look, and which we will reinstate in the coming weeks. The signals team have also been busy, with work continuing at North Weald on fitting out of the signalbox, the repeater circuits and indications. A momentous occasion was when the key section staff from North Weald to the boundary at Epping was commissioned, and is now operational. The first time the branch has had two separate operating sections since 1976, allowing a train to run in each section.
I am also delighted to report that membership of the society continues to grow, and we are also very pleased to be welcoming new faces to the team. Whether they are completely new to railways or have some previous experience, everyone is very welcome and treated equally within our friendly team.
Report compiled by Simon Hanney, GM.
December 13th, 2010
Progress Update w/e 12th Dec
Its been another busy and eventful week down Epping Ongar. Monday saw Simon attending the North Weald Parish Council meeting, as we work to strengthen the links with our local communities.
The Tuesday gang made good progress, continuing work in the Meeting & Training Room, applying undercoat to the newly plastered walls, and also continuing the restoration work on the benches which will grace our Waiting rooms.
We collected some signalling items from Network Rail later on in the week, and are very grateful to the teams for their support and assistance. A number of these items are very important as we work to advance the signalling of both North Weald and Ongar’s sites.
The Thursday gang continued work on the engineering elements, including attending to the compressor pump on the 03 and battery maintenance on our fleet. The Carriage team are continuing their work on the 117 DMU, repanelling the interior and returning it to its 1950′s condition.
During the week, we saw the first point laid at Ongar, and several panels of track positioned as we start to re-lay the new station throat (see the previous posting below), and the exciting news about the agreement to purchase the 3CIG “Lymmy Slammer” Farringford (see News page for details).
The weekend saw several teams all working towards the re-opening:
The signals team worked on various signalling tasks, part of the team installing the signal box instrument for the level crossing gate release, checking that the newly made gate release keys worked in the instrument and the locks on the gates themselves as well as starting to alter the lever bands on the signal lever controls. Another team worked in the relay room commissioning the controls for the train detection circuits, further signaller’s indications in the signal box and then wiring the control unit for the one train working system between North Weald and Epping. There is still plenty to do with the brining in to use of the signalling controls and the installing of the semaphore signals outside still outstanding.
The Track gang continued work between Ongar and Blake Hall on fixing issues with the alignment of the rails, so its a smooth and safe ride, and as we move towards needing to shunt more items between stations.
Meanwhile Bob, Rodger and Simon attended the North Weald Community Day with the railway stand on Sunday. We were delighted to be invited to this event, to both have the opportunity to inform the local community about what is happening at the railway, answer questions and encourage more local people to get involved with the friendly volunteer team down their local heritage railway.
December 8th, 2010
Track Laying Commences at Ongar
November 30th, 2010
Progress Update w/e 27th Nov
November 17th, 2010
Progress Update – Late Oct / November
Its been a busy few weeks at EOR. Work has been continuing at North Weald installing the signalling structures. These have had foundations dug, reinforcing cages made, concrete poured and then once set, the various components craned onto the foundations. This includes both the distant signals, the home signals with the routes (both bi-directional working and bay platform), and an outer home to allow us to shunt in the station while there is a train between Ongar and North Weald.
Many of these structures have been assembled and some restored over the last 2 years, and seeing them installed and standing tall is a major step forwards as we get the branch ready for passenger trains. The signalling has been designed with the 10 year Strategic Plan in mind and will be very flexible, both being able to be switched into “automatic mode” when only one shuttle train is working, but when required trains can come from either direction into both main platforms, and allow access into the new sidings and bay platform.
It has been commented that as many of the heritage “searchlight” signals were from the Colchester area, that our “37” (D6729) which regularly worked in this area will have been signalled and recognise many of these from their former locations!
Work has been continuing at Ongar and North Weald on the coaches, with good progress being made on the 117 DMU. The Carriage group are slowly growing in number and are always got a friendly welcome for new faces. With the fitting out of the 117, plus work on the steam set still to be undertaken, there is nice variety of rewarding projects for all tastes.
Our track team have been continuing work on correcting the rail alignment, in particular focusing on a section just to the east of the former Blake Hall station. The engineering team have also been continuing the work on the Ruston, and have been installing new windows and are turning their attentions to the cab interior.
The Telecoms team have also been beavering away in the background, and had a major step forward with the exchange now up and running. The team have a forward plan, and many of the routes for the phones have been included within the general works plan, so as the railway progresses, additional extensions can be easily added for key locations.
The Stations work team have been continuing work at Ongar, and the Meeting & Training room is coming together. We have been delighted to recently be gifted the redundant stove from Farringdon Station by Network Rail, which is being restored by our team prior to installing so it can once again provide warmth inside the Ongar Porter’s Room.
The team have also been following the installing of the new railings around the front of Ongar station. These have been manufacturer by Anvil Shutters http://www.anvilshutters.co.uk/ carefully following an original Great Eastern pattern to be in keeping with the station, enabling us to keep the site secure and prevent children straying from the Picnic area onto the busy high street.

The Great Eastern style railings during installation at Ongar. Following installing in red oxide, these are being top-coated in black
We have been delighted to welcome some new faces down the railway over the last couple of weeks, and a big thanks to all the team leaders and teams for all their hard work as we get the branch ready for steam and diesel locomotive hauled trains.
Report by Simon Hanney, General Manager.








